Facility preparation
Complete the pre-installation checklist to make sure your gym is ready for the delivery of EGYM Equipment. Refer to the Facility Preparation Guide for more details.
Pre-installation checklist
Complete this checklist before delivery.
Secure a broadband connection with a bandwidth of at least 5 Mbit/s (download), 1 Mbit/s (upload) per EGYM machine (see Network requirements).
Note
Contact your internet service provider as soon as possible. An active internet connection is required for installation.
Make an appointment with a qualified IT technician.
Activate a DHCP (Dynamic Host Configuration Protocol) server.
Set DHCP lease time to a maximum of 12 hours.
Exclude IP address ranges 10.9.x.x and 10.11.x.x in the DHCP server.
Ensure the IP address pool is large enough for 2x the number of planned machines (>100 recommended).
Configure firewall to allow EGYM IP addresses and ports.
Confirm whether RFID wristbands are included in your order or need to be ordered separately, or
Verify third-party RFID compatibility.
Check with EGYM Order Management whether a scale is included in your order or needs to be added.
(Optional) Add a platform scale or a body composition scale to your order.
If you order a body composition scale, start the integration process with the scale manufacturer (see Scale integration overview).